Sunday, March 13 - Saturday, March 19, 2022
SEPTEMBER 2020 WEEKLY UPDATES
Sunday, September 20, 2020 - Saturday, September 26, 2020
Contractor continued DC Water trench excavation and installed 24-inch PCC Pipe Phase-2 work area.
Contractor continued excavation work on Oregon Avenue Phase-2 work zone.
Contractor continued restoration of Outfall #2 and construction of Endwall EW3-1 and Backfilled.
Contractor trench excavated and placed Electrical Duct Bank at Phase-2 work zone and backfilled.
Contractor milling 2-inch asphalt on Chestnut Street and Oregon Avenue ready to place HMA wearing course on Phase-1 work zone.
Contractor continued to work on the final 12.5MM Surface Course paving on Chestnut Street intersection with Oregon Avenue Phase-1 work zone.
Contractor at Phase-2 work zone excavated and installed DCPLUG Manhole M7
Contractor installed catch basin connection pipe.
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, September 13, 2020 - Saturday, September 19, 2020
Contractor continued the sewer manhole installation at Sta.110+67 to 112+68 and backfilled at Phase-2 work area.
Contractor continued tree cutting at the front of House #5724 and #5728 at Phase-2 work zone.
Contractor excavated and installed Sewer Manhole MH2-3 at Phase-2 work zone.
Contractor trench excavated and placed Electrical Duct Bank at Phase-2 work zone.
Contractor excavated and installed PCC Curb and Gutter on Western Avenue at remnant of Phase-1 work zone.
Contractor continued to work on the Permeable Paver LID18-3 on Phase-1 work zone
Contractor at Phase-1 work zone excavating activity to place wheelchair, curb and gutter.
Contractor prep. Base course at Phase-1 work zone (Wise Road) for receiving 19MM HMA final course.
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per designed.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, September 6, 2020 - Sunday, Saturday 12, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1A.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per designed.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention work LID installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor excavating for manhole installation at Phase-2 work area.
Contractor backfilling trench after installation on DC-Water 18-inch PCC sewer pipe at Phase-2 work zone.
Contractor formed and poured PCC coping wall behind sidewalk for erosion mitigation at remnant of Phase-1 work zone.
Contractor excavated and placed Permeable Pavers for LID18-3 on Western Avenue at remnant of Phase-1 work zone.
Contractor excavated and installed 18-inch sewer pipe and manhole for DC-Water installation on Phase-2 work zone.
Contractor continued to work on the NPS land provided for new Office Trailer location on Phase-2 work zone.
Contractor at Phase-1 work zone backfilling the coping wall behind Wheelchair Ramp
Contractor at Phase-1 work zone installing remnant of topsoil and seeding
Sunday, August 30, 2020 - Saturday, September 5, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1A.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention work LID installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor placed and graded Topsoil and seeding the embankment landscape area at Phase-1 work zone.
Contractor placed and graded Topsoil and seeding the embankment landscape area at Phase-1 work zone.
Contractor continued to work on the DCPLUG installation of duct bank on Phase-2 work zone.
Contractor continued to work on the DCPLUG installation of duct bank on Phase-2 work zone.
Contractor at Phase-1 work zone installing remnant Bioswale LID17-8.
Contractor at Phase-1 work zone installing remnant of Permeable Paver LID18-3 on Western Avenue
Contractor at Phase-1 work zone installing remnant of Permeable Paver LID18-3 on Western Avenue
Contractor at Phase-1 work zone installing remnant of Permeable Paver LID18-3 on Western Avenue