APRIL 2020 WEEKLY UPDATES
Sunday, April 19, 2020 - Saturday, April 25, 2020
Contractor for DC Water excavated hole and installed Catch Basin (CB13-3) on Oregon Ave & backfilled
Contractor for DC Water excavated and installed Catch Basin (CB13-3) on Oregon Ave & backfilled
Contractor for DC Water excavated hole and installed Catch Basin (CB13-3) on Oregon Ave & backfilled
Contractor on Oregon Avenue, S of Birch Street installed DC Plug M32 manhole
Contractor for DC Water on Oregon Avenue started the 8-inch dia. ductile water main installation
Contractor backfilling conc encased conduit trench at STA 161+10
Contractor for DC Plug PEPCO work only breaking rock for trench on Western Ave
Contractor for DC Water excavated hole through Catch Basin (CB13-1) location installed Basin Connect & backfilled
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue
-
Management of Stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns
Sunday, April 12, 2020 - Saturday, April 18, 2020
CP for DC Water excavated hole Catch Basin (CB16-1) at STA 178+92 offset 11'LT on Oregon Ave & backfilled
CP for DC Water excavated hole Catch Basin (CB15-5) at STA 174+64 offset 11'LT on Oregon Ave & backfilled
Contractor for DC Plug Electrical conduit installation from STA 90+15.94 to 90+55 RT on Western Ave
CP for DC Water excavated hole Catch Basin (CB15-5) at STA 174+64 offset 11'LT on Oregon Ave & backfilled
Contractor excavated hole 48in dia Sewer Manhole (MH13-5) on Dogwood St & backfilled
Contractor for DC Water on Chestnut St Phase 1B installed Storm Drain STA 74+81.5 to 75+07 LT & MH at STA 75+74.50 offset
Contractor backfilled excavated trench and manhole, paved and opened closed lane for traffic.
Contractor excavated trench, installed 68.25' 18in PCC Pipe lateral & backfilled
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANCs
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue
-
Management of Stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANCs on Stakeholder request and resolution of safety concerns
Sunday, April 5, 2020 - Saturday, April 11, 2020
Capitol Paving for DC Water excavated hole & installed 48 dia MH13-5 STA 68+44LT on Birch Street & backfilled
CP on Daniel Ln from STA 173+33RT to 85+73 offset 4'LT installing 4in-4W PVC conduit & enveloped with concrete, 45LF
CP on Birch St from STA 165+15 to STA 68+38.35 offset 3'RT installing 4in-4W PVC conduit and enveloped with concrete, 43LF
Omni for CP from STA 164+35 to 165+15RT installing 4W- 4in PVC conduit and enveloped with concrete, 80LF
Capitol Paving from Chestnut St to Western Ave on Oregon Ave Phase 1B started installing Temporary (Snow) Fence
Omni backfilling and compacting DC Plug Electric PVC conduit from STA 164+35 to 165+15RT
Capitol Paving from Chestnut St to Western Ave on Oregon Ave Phase 1B started milling hard surface for Common Excavation
CP for DC Water excavated trench & installed 44.5LF of 18inch RCC Pipe lateral from STA 162+70 to 68+44LT & backfilled
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue
-
Management of Stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns
Sunday, March 29, 2020 - Saturday, April 4, 2020
Contractor placed 1st lift for 4-inch on Oregon Ave, Phase 1A from STA 171+10 to 171+38
Contractor excavated, graded and placed GAB and 8-inch asphalt base on Oregon Ave, Phase 1A-2 at Chestnut Street
Contractor placed 2nd lift for 4-inch on Oregon Ave, Phase 1A from STA 171+10 to 171+38
Contractor placing asphalt base on Oregon Avenue.
Contractor built up manhole cover with brick and mortar and also for MH invert flow line
Contractor adjusting Frame & Cover with bricks to grade and dressed in concrete.
Contractor at STA 172+11RT, on MH15-1, adjusted Frame & Cover with bricks to grade and dressed in concrete
Contractor at STA 174+24 to 174+75 Bioswale - LID14-3 laid Sod to complete installation
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue
-
Management of Stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns