top of page

APRIL 2020 WEEKLY UPDATES

Sunday, April 19, 2020 - Saturday, April 25, 2020
Progress Summary:
  1. Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.

  2. Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.

  3. Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.

  4. Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents.

  • Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation

  • Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue

  • Management of Stakeholder’s email database and communication tracker

  • Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns

Sunday, April 12, 2020 - Saturday, April 18, 2020
Progress Summary:
  1. Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A. 

  2. Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation. 

  3. Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes. 

  4. Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting. 

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents. 

  • Team continued to reach out to neighbors within the corridor about the active work and adjusted activities. 

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANCs 

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications 

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation 

  • Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue 

  • Management of Stakeholder’s email database and communication tracker 

  • Email and phone correspondence with ANCs on Stakeholder request and resolution of safety concerns 

Sunday, April 5, 2020 - Saturday, April 11, 2020
Progress Summary:
  1. Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.

  2. Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.

  3. Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.

  4. Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents.

  • Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation

  • Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue

  • Management of Stakeholder’s email database and communication tracker

  • Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns

Sunday, March 29, 2020 - Saturday, April 4, 2020
Progress Summary:
  1. Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.

  2. Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.

  3. Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.

  4. Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents.

  • Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation

  • Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue

  • Management of Stakeholder’s email database and communication tracker

  • Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns

bottom of page