top of page

FEBRUARY 2020 WEEKLY UPDATES

Sunday, February 23, 2020 - Saturday, February 29, 2020
Progress Summary:
  1. Contractor continued minimal leftover Pepco trench excavation at several locations on phase 1A. 

  2. Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation. 

  3. Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes. 

  4. Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. 

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents. 

  • Team continued to reach out to neighbors within the corridor about the active work and adjusted activities. 

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s 

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications 

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation 

  • Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue 

Sunday, February 16, 2020 - Saturday, February 22, 2020
Progress Summary:
  1. Contractor continued minimal leftover Pepco trench excavation at several locations on phase 1A. 

  2. Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation. 

  3. Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes. 

  4. Contractor continued roadway excavation and building up the new roadway on the NB lane from Western Avenue limit to Beech Street. 

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents. 

  • Team continued to reach out to neighbors within the corridor about the active work and adjusted activities. 

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s 

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications 

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation 

  • Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue 

Sunday, February 9, 2020 - Saturday, February 15, 2020
Progress Summary:
  1. Contractor continued minimal leftover Pepco trench excavation at several locations on phase 1A. Contractor continued DC-Plug concrete encasement duck bank installation. Contractor continued the installation of PVC conduit of different sets; (8) 4” Ø electrical pipe, (6) 4” Ø electrical pipe, (4) 4” Ø electrical pipe and (2) 4” Ø electrical pipe and connecting the conduits into the installed manholes. 

  2. Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, and manhole installations. 

  3. Contractor continued trench backfilling after removal of the trench boxes. Contractor continued to install conduit bends to the installed electrical manholes. Manhole recessed conduit entries were sealed with class B concrete. 

  4. Contractor continued roadway excavation and building up the new roadway on the NB lane from Western Avenue limit to Daniel Lane. 

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents. 

  • Team continued to reach out to neighbors within the corridor about the active work and adjusted activities. 

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s 

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications 

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation 

  • Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue 

Sunday, February 2, 2020 - Saturday, February 8, 2020
Progress Summary:
  1. Contractor continued minimal leftover Pepco trench excavation at several locations. Contractor continued DC-Plug concrete encasement duck bank installation. Contractor continued the installation of PVC conduit of different sets; (8) 4” Ø electrical pipe, (6) 4” Ø electrical pipe and (4) 4” Ø electrical pipe and connecting the conduits into the installed manholes. 

  2. Contractor continued DC-Water sanitary sewer manholes and sanitary sewer RC pipes for connection, and manhole installations. 

  3. Contractor continued trench backfilling after removal of the trench boxes. Contractor continued to install conduit bends to the installed electrical manholes. Manhole recessed conduit entries were sealed with class B concrete. 

  4. Contractor continued roadway excavation and building up the new roadway on the NB lane. 

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents. 

  • Team continued to reach out to neighbors within the corridor about the active work and adjusted activities. 

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANCs 

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications 

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation 

  • Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue 

bottom of page