APRIL 2021 WEEKLY UPDATES

Sunday, April 25, 2021 - Saturday, May 1, 2021
Progress Summary:
  1. Contractor continued minimal leftover activities at several locations on Phase 2.

  2. Contractor continued to build roadway on several locations on Modified Phase 3: hard surface milling
    operation, setting concrete barriers, installing silt fences and continued to install utilities as per design.

  3. Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll
    Drive.

  4. Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
    on MOT to begin the Bridge work.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected
    residents.

  • Team continued to reach out to neighbors within the corridor about active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications.

  • Management of stakeholder’s email database and communication tracker.

  • Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.

Sunday, April 18, 2021 - Saturday, April 24, 2021
Progress Summary:
  1. Contractor continued minimal leftover activities at several locations on Phase 1.

  2. Contractor continued minimal leftover activities on Phase 2.

  3. Contractor continued to build roadway on Phase 3: hard surface milling operation, setting concrete barriers, installing silt fences and continued to install utilities as per design.

  4. Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll Drive.

  5. Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DC PLUG work.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents.

  • Team continued to reach out to neighbors within the corridor about active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications.

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.

  • Management of stakeholder’s email database and communication tracker.

  • Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.

Sunday, April 11, 2021 - Saturday, April 17, 2021
Progress Summary:
  1. Contractor continued minimal leftover activities at several locations on Phase 1.

  2. Contractor continued minimal leftover activities on Phase 2.

  3. Contractor continued to build roadway on Phase 3: hard surface milling operation, setting concrete barriers, installing silt fences and continued to install utilities as per design.

  4. Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll Drive.

  5. Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DC PLUG work.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents.

  • Team continued to reach out to neighbors within the corridor about active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications.

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.

  • Management of stakeholder’s email database and communication tracker.

  • Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.

Sunday, April 4, 2021 - Saturday, April 10, 2021
Progress Summary:
  1. Contractor continued minimal leftover activities at several locations on Phase 1.

  2. Contractor continued minimal leftover activities on Phase 2.

  3. Contractor continued to build roadway on Phase 3: hard surface milling operation, setting concrete barriers, installing silt fences and continued to install utilities as per design.

  4. Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll Drive.

  5. Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
    on DC PLUG work.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected residents.

  • Team continued to reach out to neighbors within the corridor about active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications.

  • Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.

  • Management of stakeholder’s email database and communication tracker.

  • Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.