Sunday, March 13 - Saturday, March 19, 2022
APRIL 2021 WEEKLY UPDATES
Sunday, April 25, 2021 - Saturday, May 1, 2021
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 2.
-
Contractor continued to build roadway on several locations on Modified Phase 3: hard surface milling
operation, setting concrete barriers, installing silt fences and continued to install utilities as per design. -
Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll
Drive. -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
on MOT to begin the Bridge work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Management of stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.
Sunday, April 18, 2021 - Saturday, April 24, 2021
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued minimal leftover activities on Phase 2.
-
Contractor continued to build roadway on Phase 3: hard surface milling operation, setting concrete barriers, installing silt fences and continued to install utilities as per design.
-
Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll Drive.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DC PLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.
-
Management of stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.
Sunday, April 11, 2021 - Saturday, April 17, 2021
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued minimal leftover activities on Phase 2.
-
Contractor continued to build roadway on Phase 3: hard surface milling operation, setting concrete barriers, installing silt fences and continued to install utilities as per design.
-
Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll Drive.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DC PLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.
-
Management of stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.
Sunday, April 4, 2021 - Saturday, April 10, 2021
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued minimal leftover activities on Phase 2.
-
Contractor continued to build roadway on Phase 3: hard surface milling operation, setting concrete barriers, installing silt fences and continued to install utilities as per design.
-
Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll Drive.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
on DC PLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.
-
Management of stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.