Sunday, March 13 - Saturday, March 19, 2022
MAY 2021 WEEKLY UPDATES
Sunday, May 23, 2021 - Saturday, May 29, 2021
Progress Summary:
-
Contractor continued minimal remnant work activities at several locations on Phase 2.
-
Contractor continued to build roadway on several locations on Modified Phase 3: continued with utilities
installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon Knoll
(Both NPS and Resident Side), now working for preparation to switch traffic and work zone. -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
around the Pinehurst Bridge assembling all prescribed utility work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, May 16, 2021 - Saturday, May 22, 2021
Progress Summary:
-
Contractor continued minimal remnant work activities at several locations on Phase 2.
-
Contractor continued to build roadway on several locations on Modified Phase 3: continued with utilities
installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon Knoll
(Both NPS and Resident Side), now working for preparation to switch traffic and work zone. -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
around the Pinehurst Bridge assembling all prescribed utility work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Management of stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.
Sunday, May 9, 2021 - Saturday, May 15, 2021
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 2.
-
Contractor continued to build roadway on several locations on Modified Phase 3: hard surface milling
operation, setting concrete barriers, installing silt fences and continued to install utilities as per design. -
Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll
Drive. -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
to begin the Bridge work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, May 2, 2021 - Saturday, May 8, 2021
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 2.
-
Contractor continued to build roadway on several locations on Modified Phase 3: hard surface milling
operation, setting concrete barriers, installing silt fences and continued to install utilities as per design. -
Contractor continued roadway excavation on Oregon Avenue from Rittenhouse Lane to Oregon Knoll
Drive. -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
on MOT to begin the Bridge work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Management of stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.