Sunday, March 13 - Saturday, March 19, 2022
DECEMBER 2020 WEEKLY UPDATES
Sunday, December 20, 2020 - Saturday, December 26, 2020
Contractor excavated trench and placed PVC conduits for electrical signal work.
Contractor excavated trench and placed PVC conduits for electrical signal work.
Contractor adjusting the top of Catch Basin CB2-3.
Contractor installed fiber glass conduit at Phase 3D1
Contractor installed form and placed concrete for PCC Curb and Gutter Phase-2B.
Contractor continued with GAB levelling and compaction for the roadway construction on Phase-2B.
Contractor continued the Catch Basin installation top adjustment CB2-6 and CB3-1
Contractor excavated trenched and began DC PLUG PVC installation
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, December 13, 2020 - Saturday, December 19, 2020
Contractor observed discharge into outlet #3.
Contractor observed E&S functionality at Oregon Avenue and Rittenhouse Street.
Contractor adjusting the top of Catch Basin CB2-3.
Contractor excavated and installed Triple Catch Basin CB7-1
Contractor began milling operation on Modified Phase-3 from Tennyson Street to Oregon Knolls Drive.
Contractor excavated, installed and adjusted top cover of the Catch Basin CB2-1 and CB2-4.
Contractor continued the Catch Basin installation CB7-1 and Connection pipe to Manhole MH7-1
Contractor excavated trenched and began DC PLUG PVC installation
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, December 6, 2020 - Saturday, December 12, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor installed DCPLUG Conduit.
Contractor excavated full depth roadway and placed Geotextile and GAB.
Contractor rolled GAB after spreading on top of Geotextile material.
Contractor continued to work on DCPLUG Punchlist on Phase-1.
Contractor excavated trench and installed 8-inch DIP and trench backfilled.
Contractor excavated, installed DCWATER 12-inch DIP water main.
Contractor excavated roadway full depth.
Contractor continued full depth road excavation in preparation to place GAB.
Sunday, November 29, 2020 - Saturday, December 5, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor excavated to install Triple Standard Basin CB3-7.
Contractor installing 11-LF of Ductile Iron connection pipe.
Contractor excavated and placed GAB, Wire Mesh to install 48-inch Doghouse Sewer Manhole MH5-3.
Contractor laid DCPLUG 4-2W PVC conduit pipe.
Contractor installed 8-Inch Gate Valve.
Contractor excavated, formed and placed concrete for LID2-2.
Contractor continued trench excavation and shoring while installing DC PLUG PVC pipe encased in concrete.
Contractor continued excavation, formed and poured concrete for Bioretention Planter LID2-2.