Sunday, March 13 - Saturday, March 19, 2022
MARCH 2020 WEEKLY UPDATES
Sunday, March 22, 2020 - Saturday, March 28, 2020
CP paved on 1st mat for 2nd lift on Oregon Ave, Phase 1A from STA 164+14 to 157+94RT
CP at Daniel Ln to Chestnut Street to DC Water MH, adjust raising Frame & Cover with bricks to grade
CP at Beech Street to Chestnut Street to DC Water MH, adjust raising Frame & Cover with bricks to grade - placing concrete
CP at STA 174+24 to 174+75RT excavated trench, installed Geotextile, #57 & #2 stones for Bioswale - LID15-3
CP at Catch Basin filling holes with grout
CP at Catch Basin filling holes with grout
CP at Beech Street to Chestnut Street to DC Water MH, adjust raising Frame & Cover with bricks to grade
Performed rope test run through installed PVC conduits from Dogwood (M37) to Daniel (M38)
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington
-
Gas project on Oregon Avenue
-
Management of Stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns
Sunday, March 15, 2020 - Saturday, March 21, 2020
Contractor excavating & placed GAB with fabric for roadway STA 167+28 to 167+58RT, NE. half Chestnut Street intersection
Contractor adjusting Triple Basin - CB16-2 at STA 178+92 offset 11.00' RT, formed & pour conc to final grade
Contractor at STA 168+00 to DC Plug MH, M36, remove GAB, clean, formed to adjust Frame & Cover
Contractor at STA 176+65 to 179+16RT set forms and placed concrete for PCC Curb and Gutter
Contractor at STA 174+50 to 175+00 removed & replaced Temp PCC Barriers to form close opening for access
Contractor at STA 179+11 to 179+81.5RT excavated trench, installed Geotextile, #57 & #2 Stones for Bioswale
Contractor at STA 179+11 to 179+81 began installation of sod and grass
Contractor at STA 179+11 to 179+81 began installation of sod and grass
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue
-
Management of Stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns
Sunday, March 8, 2020 - Saturday, March 14, 2020
Behind PCC Curb & Gutter backfilled with on-site material, rolled to compact for Topsoil from STA 183+50 to 190+25
CB12-5 at STA 158+60 dug hole & installed Dual Throat Water Quality Basin & Basin Connect pipe
CB12-5 at STA 158+60 dug hole & installed Dual Throat Wa-ter Quality Basin & Basin Connect pipe
Contractor set forms on compacted & approved GAB sub-base placed concrete for PCC Curb and Gutter
Roadway Undercut from STA 176+80 to 176+50RT removed & graded GAB and rolled to compact
Roadway final grading of GAB at subbase from STA 157+85 to 166+75
Excavating & placed GAB with fabric for roadway STA 166+76 to 167+28RT, SE. half Chestnut Street intersection
Excavating & placed GAB with fabric for roadway STA 166+76 to 167+28RT, SE. half Chestnut Street intersection
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue.
-
Management of Stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns.
Sunday, March 1, 2020 - Saturday, March 7, 2020
Contractor continued excavation for the installation of Dual Throat Water Quality Basin & connect Basin pipes
Contractor continued excavation for the installation of Dual Throat Water Quality Basin & connect Basin pipes
Contractor continued paving activity on Oregon Ave, from Western Ave to North of Daniel Lane STA 179+25 to 190+25
Contractor continued paving activity on Oregon Ave, from Western Ave to North of Daniel Lane STA 179+25 to 190+25
Capitol Paving installing Manhole - Electric Vault - M39 at STA 177+86
Contractor saw cut PCC Curb and Gutter for Opening as per plan for LID run-off.
CP paved on 1st base lift on Oregon Ave, Phase 1A from Western Ave to North of Daniel Lane STA 189+65 to 190+25
Contractor at STA 183+57 for DC Plug MH, M44, cut & remove asphalt to anchor Frame and Cover - placed concrete
Progress Summary:
-
Contractor continued minimal leftover Pepco trench excavation at several locations on phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor began the lid installation preparation by cutting the curb.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANCs.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue.
-
Management of Stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANCs on Stakeholder request and resolution of safety concerns.