Sunday, March 13 - Saturday, March 19, 2022
NOVEMBER 2021 WEEKLY UPDATES
Sunday, November 7, 2021 - Saturday, November 13, 2021
Progress Summary:
-
Contractor continued minimal remnant work activities at several locations on Phase 2.
-
Contractor continued to build roadway at several locations on Modified Phase 3: continued with utilities
installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon
Knolls (Both NPS and Resident Side). -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
around the Pinehurst Bridge, assembling all prescribed utility work. Built the south-side of the Bridge
Approach and now working on the north-side of the Bridge Approach.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns
Sunday, October 31, 2021 - Saturday, November 6, 2021
Progress Summary:
-
Contractor continued minimal remnant work activities at several locations on Phase 2.
-
Contractor continued to build roadway at several locations on Modified Phase 3: continued with utilities
installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon
Knolls (Both NPS and Resident Side). -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
around the Pinehurst Bridge, assembling all prescribed utility work. Built the south-side of the Bridge
Approach and now working on the north-side of the Bridge Approach.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns