MARCH 2021 WEEKLY UPDATES
Sunday, March 28, 2021 - Saturday, April 3, 2021
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued to build roadway on Phase-2: hard surface milling operation, setting concrete
barriers, installing silt fences, preparing to move office trailer behind the community garden near
Horse Stable Road, and continued to install utilities as per design. -
Contractor continued roadway excavation on SB lane from Military Road limit to Rittenhouse Street.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
on DCPLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.
-
Management of stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.
Sunday, March 21, 2021 - Saturday, March 27, 2021
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued to build roadway on Phase-2: hard surface milling operation, setting concrete
barriers, installing silt fences, preparing to move office trailer behind the community garden near
Horse Stable Road, and continued to install utilities as per design. -
Contractor continued roadway excavation on SB lane from Military Road limit to Rittenhouse Street.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
on DC PLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.
-
Management of stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.
Sunday, March 14, 2021 - Saturday, March 20, 2021
Contractor preparing for PCC Driveway repair at House #5842 on Phase 2B
Contractor excavated and about to install 3.5’ x 3.5’ DC-Plug tap hole on Phase 2B
Contractor compacting the base grade before GAB for Exposed Aggregate sidewalk
Contractor for DC-Water works trench excavated and installed 12-inch DIP
DC-PLUG conduit 4-4W PVC conduit pipe
Contractor adjusted manhole covers on Phase 2B
Contractor excavated, placed GAB, for roadwork and compacted.
Dulles Engineering on Oregon Avenue, Phase 2B, performed Infiltration Testing on LID 6-2
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on SB lane from Military Road limit to Rittenhouse Street.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DC PLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, March 7, 2021 - Saturday, March 13, 2021
Contractor preparing for PCC Driveway repair at House #5850 on Phase 2B
Contractor continued laying pavers for Permeable Concrete Unit Pavers, Type 1 for LID6-2 on Phase 2B
Contractor paved HMA Base for 2nd lift
Contractor for DC-Water works trench excavated and installed 12-inch DIP and Gate Valve
After relocation of the down guy, Contractor installing Triple Basin Catch Basin
Contractor on modified Phase 3D-2 installed Basin and Basin connection pipe
Contractor excavated, placed GAB, for PCC Curb and Gutter and Wheelchair Ramp.
Contractor saw cut hot mix to adjust manhole cover.
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on SB lane from Military Road limit to Rittenhouse Street.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DCPLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, February 28, 2021 - Saturday, March 6, 2021
Contractor preparing for PCC Driveway repair at House #5820 on Phase 2B
Contractor preparing for PCC to Asphalt driveway repair at House #5826 on Phase 2B
Contractor continued Manhole cover adjustment and placed brick liner.
Contractor continued Manhole cover adjustment and placed brick liner.
Contractor installing MOT advance detour warning signs
Contractor on modified Phase 3D-1 backfilled behind PCC Curb and Gutter and placed topsoil and seeding.
Contractor excavated, placed GAB, for LID 6-2 and poured edge restraint lip.
Contractor excavated, placed GAB, for LID 6-2 and poured edge restraint lip.
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on SB lane from Military Road limit to Rittenhouse Street.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DCPLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns