DECEMBER 2021 WEEKLY UPDATES

Sunday, December 19, 2021 - Saturday, December 25, 2021
Progress Summary:
  1. Contractor continued minimal remnant work activities at several locations on Phase 2.

  2. Contractor continued to build roadway at several locations on Modified Phase 3: continued with utilities
    installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
    Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon
    Knolls (Both NPS and Resident Side).

  3. Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
    around the Pinehurst Bridge, assembling all prescribed utility work. Built the south-side of the Bridge
    Approach and now working on the north-side of the Bridge Approach.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected
    residents.

  • Team continued to reach out to neighbors within the corridor about active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications

  • Management of stakeholder’s email database and communication tracker

  • Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns

Sunday, December 12, 2021 - Saturday, December 18, 2021
Progress Summary:
  1. Contractor continued minimal remnant work activities at several locations on Phase 2.

  2. Contractor continued to build roadway at several locations on Modified Phase 3: continued with utilities
    installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
    Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon
    Knolls (Both NPS and Resident Side).

  3. Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
    around the Pinehurst Bridge, assembling all prescribed utility work. Built the south-side of the Bridge
    Approach and now working on the north-side of the Bridge Approach.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected
    residents.

  • Team continued to reach out to neighbors within the corridor about active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications

  • Management of stakeholder’s email database and communication tracker

  • Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns

Sunday, December 5, 2021 - Saturday, December 11, 2021
Progress Summary:
  1. Contractor continued minimal remnant work activities at several locations on Phase 2.

  2. Contractor continued to build roadway at several locations on Modified Phase 3: continued with utilities
    installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
    Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon
    Knolls (Both NPS and Resident Side).

  3. Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
    around the Pinehurst Bridge, assembling all prescribed utility work. Built the south-side of the Bridge
    Approach and now working on the north-side of the Bridge Approach.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected
    residents

  • Team continued to reach out to neighbors within the corridor about active work and adjusted activities

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications

  • Management of stakeholder’s email database and communication tracker

  • Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns

Sunday, November 28, 2021 - Saturday, December 4, 2021
Progress Summary:
  1. Contractor continued minimal remnant work activities at several locations on Phase 2.

  2. Contractor continued to build roadway at several locations on Modified Phase 3: continued with utilities
    installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
    Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon
    Knolls (Both NPS and Resident Side).

  3. Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
    around the Pinehurst Bridge, assembling all prescribed utility work. Built the south-side of the Bridge
    Approach and now working on the north-side of the Bridge Approach.

CM Community Outreach Activities

  • Communications team continued to address all work-related issues and coordinated with the affected
    residents.

  • Team continued to reach out to neighbors within the corridor about active work and adjusted activities.

  • Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s

  • Outlined targeted areas for outreach efforts and distribution of NCC notifications

  • Management of stakeholder’s email database and communication tracker

  • Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns