Sunday, March 13 - Saturday, March 19, 2022
NOVEMBER 2020 WEEKLY UPDATES
Sunday, November 22, 2020 - Saturday, November 28, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor excavating trench for electrical conduit encased PVC pipe.
Contractor installing trench shoring for DC PLUG electrical pipe installation.
Contractor Laid 12-inch DIP water main system.
Contractor began trench backfilling.
Contractor continued trench backfilling.
Contractor excavated, formed and placed concrete for LID2-1.
Contractor continued excavation and installed DCWATER Pipe
Contractor placed concrete inside the trench box ready for backfilling.
Sunday, November 15, 2020 - Saturday, November 21, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor installing electrical manhole.
Contractor began conduit trench excavation.
Contractor laid electrical PVC conduit duct bank and placed concrete.
Contractor laid electrical PVC conduit duct bank and placed concrete.
Contractor began trench backfilling.
Contractor about to install DC PLUG manhole.
Contractor excavated trench for the conduit installation.
Contractor placed concrete inside the trench box ready for backfilling.
Sunday, November 8, 2020 - Saturday, November 14, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor continued backfilling behind PCC Curb and Gutter and seeded.
Contractor continued to adjust Manhole frames and covers encased in concrete.
Contractor Laid Brick with mortar to build the Chanel Invert for water flow.
Contractor began Tree Planting as per plan on Phase-1 work zone.
Contractor began Tree Planting as per plan on Phase-1 work zone.
Contractor began Tree Planting as per plan on Phase-1 work zone.
Contractor installed detour MOT signs for Phase 2B.
Contractor moving Temporary Barrier from Military Road to Rittenhouse Street for Phase 2B.
Sunday, November 1, 2020 - Saturday, November 7, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor continued roadway manhole adjustment of Frame and Cover for MH1-2, MH2-1, MH2-1, MH7-1, MH6-1, and MH6-2
Contractor continued roadway manhole adjustment of Frame and Cover for MH1-2, MH2-1, MH2-1, MH7-1, MH6-1, and MH6-2
Contractor placing Topsoil between Rittenhouse Street and Horse Stable Road.
Contractor sawcut to adjust elevation of the Manhole.
Contractor installed pole foundation for traffic light.
Contractor paved base course on Oregon Avenue Phase 2A-1 by Horse Stable Road.
Contractor placed Asphalt by Horse Stable Road on Oregon Avenue.
Contractor continued to lay brick with mortar and build the channel flow inverts.