AUGUST 2020 WEEKLY UPDATES
Sunday, August 16, 2020 - Saturday, August 22, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1A.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention work LID installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns

Contractor adjusting Catch Basins on Oregon Avenue.

Contractor installing PCC Curb and Gutter on Phase-1 work area.

Contractor finishing remnant of LID’s on Phase-1 work zone

Contractor finishing remnant of Catch Basin top adjustment on Phase-1 work zone

NPS visit - Outfall #7 on Oregon Avenue at Daniel Lane existing condition

Contractor Milling operation on Phase-2 Common Excavation work

Contractor installing temporary barrier end treatment.

Contractor Placed DCPLUG Manhole by ST John’s College High School.
Sunday, August 9, 2020 - Saturday, August 15, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1A.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention work LID installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns

Contractor installed temporary road pavement to widen the existing road in preparation for Phase 2 work.

Contractor placed second layer of 4-inch asphalt on Oregon Avenue and Beech Street.

Contractor installed Auto Flushing Unit on Oregon Avenue Sta.188+00

Contractor installed PVC pipes for manhole connection into the Auto Flushing Unit.

Contractor removed downed tree on Oregon Avenue over the weekend.

Contractor at various location placed asphalt to ramp around PCC curb and Gutter, Manhole.

Contractor Closed NB lane Oregon Avenue and began PCC barrier installation.

Contractor placing PCC Concrete Barrier and removed Traffic Cones.
Sunday, August 2, 2020 - Saturday, August 8, 2020
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns

Contractor on Western Avenue, laying Permeable Concrete unit Pavers for LID18-4.

Contractor paved 8-inch Base Course on Oregon Avenue.

Contractor installed PVC pipes, Laid Geotextile Fabric, Waterproof membrane, #57 double washed stone (LID12-4).

Contractor placed PVC pipe laid Geotextile Fabric, Waterproof membrane & #57 washed stone.

Contractor at various LID location placed river rocks and filter.

Contractor placing topsoil and seeding.

Contractor into various LID’s Concrete Check Dams placed River Rocks.

Contractor at various LID location placed river rocks and filter.