Sunday, March 13 - Saturday, March 19, 2022
MAY 2020 WEEKLY UPDATES
Sunday, May 10, 2020 - Saturday, May 16, 2020
CP at PT STA: 175+40.78 to 176+30.78 (LID 15-4) concrete was placed and finished as per the design.
Chlorination test
Contractor installing 12” Ductile Iron Pipe
Installation of 14-inch DIP
Contractor at PT STA: 175+40.78 to 176+30.78 (LID 15-4) installation of the form work on the sidewalk.
Installation of 18” PCC pipe
Taking of Water to be tested for contamination
Contractor at STA: 171+03.80 to 172+74.55 (LID 14-4) concrete was placed (roadway side) and finished as per the design.
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue
-
Management of Stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns
Sunday, May 3, 2020 - Saturday, May 9, 2020
Contractor excavated and placed GAB to set form for PCC Curb & Gutter within Bioretention LID15-2
Contractor continued 8” diameter ductile water main installation
Contractor Daniel Lane lateral 8-inch diameter ductile iron water main installation.
Contractor continued installation of 12” ductile iron water main
Installation of 8” DIP
Installation of 12” GATE VALVE
Contractor excavated & placed GAB for PCC Curb & Gutter within Bioretention LID16-2
Site condition at Chestnut on Oregon Ave - Rainy
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue
-
Management of Stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on Stakeholder request and resolution of safety concerns