Sunday, March 13 - Saturday, March 19, 2022
FEBRUARY 2021 WEEKLY UPDATES
Sunday, February 21, 2021 - Saturday, February 27, 2021
Contractor preparing for PCC Driveway repair at House #5850 on Phase 2B
Contractor preparing for PCC to Asphalt driveway repair at House #5860 on Phase 2B
Contractor continued excavation and installed Permeable Concrete Unit Paver Type 1 LID 6-2.
Contractor performed Infiltration Test on LID 1-1 Permeable Concrete Unit Pavers.
Contractor besides LID6-2, set forms for PCC Curb and Gutter on Phase 2B
Contractor power washed previously placed exposed aggregate sidewalk.
Contractor poured exposed Aggregate sidewalk
Contractor excavated DC-Water main and tie in operation
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on SB lane from Military Road limit to Rittenhouse Street.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DC PLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, February 14, 2021 - Saturday, February 20, 2021
Contractor continued excavation and installing Permeable Concrete Unit Paver Type-1 for LID6-2 on Phase 2B
Contractor continued excavation and installing Permeable Concrete Unit Paver Type-1 for LID6-2 on Phase 2B
Contractor on Modified Phase 3D-1, backfilled behind PCC Curb and Gutter with on-site Material.
Contractor placed fine grading GAB and compacting on Modified Phase 3-D1
Contractor cleaning and purging catch basins on Phase 2B
Contractor excavated, placed GAB, rolled and compacted; ready for Exposed Aggregate Sidewalk.
Contractor excavated and installed Permeable Concrete Paver for LID6-2
Contractor excavated and installed Permeable Concrete Paver for LID6-2
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on SB lane from Military Road limit to Rittenhouse Street.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DC PLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Sunday, February 7, 2021 - Saturday, February 13, 2021
Contractor continued backfilling and grading behind PCC Curb and Gutter for sidewalk preparation Pha
DDOT QA/QC Technician Tested Compaction on GAB subbase for roadway and passed.
Contractor placed formwork and concrete for PCC Curb and Gutter
PEPCO Contractor transferring wires from poles obstructing construction to move the poles.
Contractor excavated and installed infiltration under sidewalk LID6-1
Contractor excavated and installed Permeable Concrete Paver for LID1-1
Contractor placing asphalt at Phase 2B
Contractor placing asphalt at Phase 2B
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor continued to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on SB lane from Military Road limit to Rittenhouse Street.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working on DC PLUG work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns