Sunday, March 13 - Saturday, March 19, 2022
SEPTEMBER 2021 WEEKLY UPDATES
Sunday, September 26, 2021 - Saturday, October 2, 2021
Progress Summary:
-
Contractor continued minimal remnant work activities at several locations on Phase 2.
-
Contractor continued to build roadway at several locations on Modified Phase 3: continued with utilities
installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon
Knolls (Both NPS and Resident Side), now working on preparation to switch traffic and work zone. -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
around the Pinehurst Bridge, assembling all prescribed utility work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns
Sunday, September 19, 2021 - Saturday, September 25, 2021
Progress Summary:
-
Contractor continued minimal remnant work activities at several locations on Phase 2.
-
Contractor continued to build roadway at several locations on Modified Phase 3: continued with utilities
installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon
Knolls (Both NPS and Resident Side), now working on preparation to switch traffic and work zone. -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
around the Pinehurst Bridge, assembling all prescribed utility work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns
Sunday, September 12, 2021 - Saturday, September 18, 2021
Progress Summary:
-
Contractor continued minimal remnant work activities at several locations on Phase 2.
-
Contractor continued to build roadway at several locations on Modified Phase 3: continued with utilities
installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from
Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon
Knolls (Both NPS and Resident Side), now working on preparation to switch traffic and work zone. -
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working
around the Pinehurst Bridge, assembling all prescribed utility work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected
residents. -
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns
Sunday, September 9, 2021 - Saturday, September 11, 2021
Progress Summary:
-
Contractor continued minimal remnant work activities at several locations on Phase 2.
-
Contractor continued to build roadway at several locations on Modified Phase 3: continued with utili-ties installation across the Pinehurst Branch, finished asphalt base road pavement (NPS side) from Rittenhouse Street to Tennyson Street. Finished Asphalt base from Tennyson Street to Oregon Knolls (Both NPS and Resident Side), now working on preparation to switch traffic and work zone.
-
Contractor continued to build roadway on Phase-3 approved modified MOT and is currently working around the Pinehurst Bridge, assembling all prescribed utility work.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANCs on stakeholder requests and resolution of safety concerns