Sunday, March 13 - Saturday, March 19, 2022
JUNE 2020 WEEKLY UPDATES
Sunday, June 21, 2020 - Saturday, June 27, 2020
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Con-tractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor set form for PCC Curb & Gutter & Wheelchair Ramp on Daniel Ln North & South corners
Contractor set form & placed concrete for PCC Curb & Gutter & Wheelchair Ramp on Daniel Ln North & South corners
Contractor at SW corner of Oregon Avenue and Dogwood Street, form & pour to adjust CB14-6.
Contractor excavated, placed GAB and placed concrete for 8’ x 60’ PCC Bus Pad on Oregon Avenue
Contractor installed 4” underdrain from CB12-4 to LID 12-3 and CB12-6, to LID 13-1
Contractor excavated on Dogwood Street to subgrade & placed GAB
Contractor for PCC Curb & Gutter and Wheelchair Ramp graded GAB and formed.
Contractor Paving on Oregon Ave, from Western to Daniel
Sunday, May 31, 2020 - Saturday, June 6, 2020
Contractor placed GAB on Oregon Avenue Roadway from Sta.189+69 to Sta.186+38
Contractor performing compaction of subgrade
Contractor set forms & placed concrete for the installation of check dams to LID16-3 facility from Sta.179+11 to Sta.180+01
Thrust block construction
Contractor performing excavation for water service connection
Contractor placing GAB material
PEPCO continued in front of House #6840 on Oregon Ave, STA 165+80LT installed Pole for removal of obstructing Pole.
Contractor set forms for the installation of concrete check dams to LID16-3 facility from Sta.179+11 to Sta.180+01
Progress Summary:
-
Contractor continued minimal leftover Pepco manhole cover adjustment at several locations on Phase 1A.
-
Contractor continued DC-Water sanitary sewer manholes and sanitary sewer 24-inch and 18-inch RC pipes for connection, manhole installations and catch basin installation.
-
Contractor continued to build the roadway; installing geotextile, GAB, and asphalt base course. Contractor continued trench backfilling after removal of the trench boxes.
-
Contractor continued roadway excavation, building up the new roadway on the NB lane from Western Avenue limit to Beech Street and installing PCC curb and gutter. Contractor continued excavation for the LID installation preparation and curb cutting.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about the active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s.
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications.
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation.
-
Communicated with Chatsworth community and HOA President on behalf of Washington Gas project on Oregon Avenue.
-
Management of stakeholder’s email database and communication tracker.
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns.