Sunday, March 13 - Saturday, March 19, 2022
OCTOBER 2020 WEEKLY UPDATES
Sunday, October 25, 2020 - Saturday, October 31, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor continued GAB grading and compaction for PCC Curb and Gutter and Asphalt placement.
Contractor continued Channel Flow Invert built for manhole MH5-1 by laying bricks and mortar.
Contractor installed Special Stamped concrete driveway for House #6830
Contractor installed Special Stamped concrete driveway for House #6830
Contractor formed and placed PCC Wheelchair, Curb and Gutter at Military Rd. and Oregon Avenue.
Contractor formed and placed PCC Wheelchair, Curb and Gutter at Military Rd. and Oregon Avenue.
Contractor placed formwork and concrete for PCC Curb and Gutter after compaction approval.
Contractor continued to roll and compact newly placed Asphalt.
Sunday, October 18, 2020 - Saturday, October 24, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor continued to excavate for roadway construction.
Contractor continued GAB grading and compaction for PCC Curb and Gutter and Asphalt placement.
Contractor continued installation of 15-inch Basin Connection pipe.
Contractor continued installation of 14-inch Basin Connection pipe.
Contractor continued remnant work at phase-1 installing brick and mortar for the manhole invert channels.
Contractor continued installation of 15-inch Basin Connection pipe.
Contractor furnished and installed 3-inch mulch and shrubs at Bioretention Planter LID.
Contractor installed stone on filter cloth for outfall #2.
Sunday, October 11, 2020 - Saturday, October 17, 2020
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns
Contractor continued to excavate for roadway construction.
Contractor continued to install Catch Basin CB4-2.
Contractor installed formwork for PCC Curb and Gutter and placed concrete.
Contractor continued full depth excavation.
Contractor continued full depth and graded GAB compaction as QA/QC Technician checked compaction.
Contractor furnished and installed Catch Basin.
Contractor excavated, set form and placed concrete for PCC Coping wall
Contractor furnished and installed Catch Basin.
Sunday, October 4, 2020 - Saturday, October 10, 2020
Contractor continued DC Water trench excavation and installation of 18-inch PCC Pipe.
Contractor continued to backfill trench.
Contractor continued to excavate the road and graded GAB.
Contractor installed Planter Railing on LID’s.
Contractor continued full depth and graded GAB compaction as QA/QC Technician checked compaction.
Contractor continued Outfall #3 Endwall backfilled.
Contractor continued excavation, formed and poured outfall #3.
Contractor laid brick and mortar to close 2 out of 4 inlets at CB12-5 Dual Throat Water Quality Basin.
Progress Summary:
-
Contractor continued minimal leftover activities at several locations on Phase 1.
-
Contractor began to build roadway on Phase-2: hard surface milling operation, setting concrete barriers, installing silt fences, preparing to move office trailer behind the community garden near Horse Stable Road, and continued to install utilities as per design.
-
Contractor continued roadway excavation on NB lane from Military Road limit to Rittenhouse Street and installed all proposed advance warning signs. Contractor continued to finish up remaining bioretention LID work installed at Phase-1.
CM Community Outreach Activities
-
Communications team continued to address all work-related issues and coordinated with the affected residents.
-
Team continued to reach out to neighbors within the corridor about active work and adjusted activities.
-
Organized the Neighborhood Communication Committee (NCC) comprised of ANC’s
-
Outlined targeted areas for outreach efforts and distribution of NCC notifications
-
Hosted first NCC meeting with chairperson and AECOM to discuss sidewalk implementation
-
Management of stakeholder’s email database and communication tracker
-
Email and phone correspondence with ANC’s on stakeholder request and resolution of safety concerns